Saw a crew overworking their concrete on a job last week
They were still troweling the surface 4 hours after the pour, trying to get it glass smooth. The mix was way too stiff by then and they were just pulling up fines, leaving a weak top layer that will dust up in a year. I learned this the hard way on a garage floor I did 2 years ago. Now I stop all finishing work once the sheen is gone and you can walk on it without leaving prints. Has anyone else found a good rule of thumb for when to walk away from the trowel?
3 comments
Log in to join the discussion
Log In3 Comments
wren23019d ago
My rule is once the sheen disappears, I'm done.
6
thomas_butler19d ago
Yeah, that "sheen is gone" rule saved my last patio from turning into a dust bowl.